Reconstruction of the bridge in Radymno - Mosty Łódź S.A.

Reconstruction of the bridge in Radymno

The original bridge was built in 1911. In 2002, Mosty Łódź performed its reconstruction.

The work included:
  • dismantling of the lattice superstructure
  • dismantling and reconstruction of new bridgeheads
  • partial dismantling of intermediate supports, their reconstruction and construction of new caps
  • reinforcing the pillar foundations using prefabricated piles
  • construction of a new steel span structures with reinforced concrete slab
  • dpost-tensioning the superstructure and installation of traffic safety equipment and elements
  • execution of road works, including the adjustment of access to the structure

Project challenge: It was necessary to reinforce the banks of the San River as part of the project.

News and events